Tennessee State University -- Tunnel Steam Piping Investigation -- Observations
Overall plan of the steam tunnel that summarizes the observations You are here

Photo 3-3. (M-792)

Poor anchor weld on CR main anchor at DSB intersection.

Note space between anchor and support channel (at top of photo) indicating anchor weld had probably broken lose and was re-welded atop the old weld material. See comment previous photo 3-2.